Home
|
Contact Us
About Us
Overview
Management
Board of Directors
Corporate Governance
Rosemont Copper
Overview
Location
Sustainability
Project Development & Permitting
Technical Reports
News
2012
2011
2010
2009
2008
2007
2006
Investors
Overview
Stock Quote
Share Information
Analyst Coverage
Financial Reports
PFIC statement
Regulatory Filings
FAQ
RSS Feeds
Contact Us
Home
>>
Rosemont Copper
>>
Project Development & Permitting
Project Development & Permitting
2011
U.S. Forest Service published Rosemont Copper Draft Environmental Impact Statement and Issues Notice of Availability in October 2011 (
www.fs.fed.us/r3/coronado
/
)
The public comment period for the Draft Environmental Impact Statement has concluded.
Currently, Rosemont Copper has received the following permits and approvals: Construction Storm Water General Permit, Agriculture Land Clearing Permit, Air Activity Permit, Groundwater Withdrawal Permit, Type 2.02 and 3.03 General Aquifer Protection Permits, Arizona Mined Land Reclamation Plan Approval and Hazardous Waste Identification Number
2010
Draft of the Environmental Impact Statement delivered to the US Forest Service, Coronado National Forest, by the Environment Impact Statement contractor SWCA of Tucson, Arizona, for internal review.
Completed $30 million private placement with HudBay Minerals, representing an approximate 30% premium to market. All equity has now been raised for the project.
Entered into a Joint Venture Agreement with Korean Consortium consisting of Korea Resources (KORES) and LG International for 20% joint venture interest in Rosemont. Cash injection of US$176 million ($70 million for development pre-construction and US$106 million for construction) in addition to off take agreement for 30% of copper concentrate and 20% of copper cathode and molybdenum concentrates.
Entered into agreement with Silver Wheaton to purchase Rosemont's life of mine gold and silver production for cash injection of US$230 million. Represents 25% of total project capex for less than 4% of annual revenue.
Continued to build the project development team, appointing Dan Ryan as Director of Community Relations, and filling out the EPCM team with Patrick Glynn as Project Manager, Clarissa Barraza as Project Engineer, Ronald Tornberg as Senior Electrical Engineer and Ching-Sheng Hwang as Senior Civil Engineer.
Placed order for 14 Eimco AFP Mark IV tailings filter presses from FLSmidth for US$31 million. These will be used to filter the tailings slurry to 16% moisture. The filtered solids will then be transported via conveyors to the dry stack tailings facility.
Incorporated the construction work packages (CWPs) into the overall project schedule.
2009
Completed updated Feasibility Study in January 2009.
Signed agreement for purchase of 23, 250-ton Caterpillar 793F haulage trucks from Empire Southwest LLC in Mesa, Arizona. Contingent with the agreement both parties agreed on a term sheet for a capital lease of the Caterpillar trucks and other related equipment for an amount up to US$100 million. The contract value between Rosemont and Empire is approximately $82.2 million for the purchase of the 23 trucks.
2008
Signed US$29 million contract with Polysius Corp. for the purchase and delivery of a 36ft x 17.5ft EGL (effective grinding length) SAG and two 26ft x 40ft EGL ball mills, placing a sizeable deposit on this contract commitment in Q108.The Company was successful in negotiating improved financing and delivery terms from those estimated in the bankable feasibility study published in August 2007, and was pleased to complete this critical path milestone with an overall positive impact on the project schedule.
Entered into a US$42 million contract with ABB Switzerland Ltd. for the supply of three gearless mill drives in Q208. ABB's scope of supply includes a 16 MW gearless mill drive system for a 36' diameter SAG mill and two 16MW gearless mill drive systems for 26' diameter ball mills.
Awarded US$56 million agreement for the engineering, procurement and construction management ("EPCM") contract with M3 Engineering & Technology Corporation for the development and construction of the Rosemont project in Q208. M3 completed the bankable feasibility study for Rosemont in August 2007, so the Company was pleased to be able to move forward with M3 to commence design engineering.
Awarded $8.6 million contract to Sandvik for primary crusher and $65 million contract to Bucyrus International for three 495HR mining shovels.
Continued to build the project development team, appointing Rod Pace as Vice-President, Operations, Kathy Arnold as Director of Environmental and Regulatory Affairs, Fermin Samorano as Mine Manager, and Buck Andrews as Controller.
Thumb
Date
Download
February 17, 2012
Augusta Presentation
click here to download
1.68 MB
November 7, 2011
Augusta Factsheet
click here to download
350 KB
Latest
Latest News
January 23, 2012
Augusta Provides Permitting Update on its Rosemont Copper Project
October 21, 2011
Augusta Announces "Notice of Availability" for Rosemont Copper DEIS Issued by USFS
October 13, 2011
Augusta Announces Rosemont Copper DEIS Published by USFS
Click to view 3D block model
Quick Links
Date
Download
October 13, 2011
Rosemont Copper DEIS
July 6, 2011
Feasibility Study
5.00 MB
June 6, 2011
Plan of Operations
453 KB
June 4, 2011
Economic Impact
475 KB
June 3, 2011
Reclamation Plan
June 2, 2011
Infrastructure Plan
June 1, 2011
Rosemont Copper Website
May 30, 2011
News Signup
2011 Augusta Resource Corporation. All Rights Reserved.
Home
|
Rosemont Copper
|
Legal Notice
|
Contact Us
|
Powered By Q4 Web Systems
3.6.1.3509