Augusta Resource Corporation (TSXV: ARS)
(“Augusta” or the “Company”) is pleased to announce the results of a
Preliminary Assessment (“PA”) on its 100% owned Rosemont
copper/molybdenum project located in Pima County, Arizona. The PA
demonstrates that the Rosemont copper/molybdenum deposit may be
developed as a low cost open pit mine with potentially robust project
economics. All dollar figures are in United States dollars unless
otherwise indicated.
| Economic Highlights of the PA include: |
|
|
| Financial: |
Case 1 |
Case 2 |
| Net Present Value (8% discount rate) |
$442M |
$494M |
| Internal Rate of Return (IRR) |
17% |
17% |
| Cash Costs/lb. Cu (net of by-products) |
$0.42 |
$0.37 |
| Direct Capital Costs (incl. 15% contingency) |
$636M |
$806M |
| Net Present Value (8%) (excl. capital contingency) |
$499M |
$595M |
| IRR (excl. capital contingency) |
20% |
20% |
| Annual Production: |
|
|
| Copper (lbs) |
226,000,000 |
233,300,000 |
| Molybdenum (lbs) |
5,100,000 |
5,100,000 |
| Silver (oz) (as by-product credit) |
6,700,000 |
6,700,000 |
(Un-levered economics run at $1.20/lb
Copper (“Cu”), $10/lb Molybdenum (“Mo”) and $7.50/oz Silver (“Ag”) see
PA report features below for study assumptions and summary.)
Case 1 assumes a conventional open pit
mine, concentrator producing a copper sulphide concentrate, a molybdenum
concentrate (“MoS2”), and with silver as a by-product credit contained
in the copper concentrate. The copper concentrate is planned to be
shipped to smelters in the US southwest or Mexico.
Case 2 adds production from the leaching
of existing oxide copper resources (approximately 60 million tons) and
evaluates the addition of a concentrate leach circuit and a solvent
extraction/electrowinning (“SX/EW”) plant designed to produce LME grade
copper cathode. This Case assumes production of LME grade cathode
and copper concentrate shipments at a
ratio of 75/25 cathode /concentrate production. However the Company
believes that the potential full financial impact has not been optimized
in this study, as some additional overburden characterized as waste in
the mine model could potentially be leached and recovered through an
SX/EW plant. At this point, the Company has not completed enough work to
determine what quantities of this material are present. As reported in
the Company’s press release of March 27, 2006, an assay program of
existing diamond drill core in the overburden oxide zones is underway in
order to establish an additional oxide resource.
Floating cone evaluations of
potentially economic pit limits were conducted using the complete
mineral resource base including inferred mineral resources. The estimate
of measured and indicated resources above a 0.2% Cu cut-off total about
442 million tons grading 0.51% Cu and 0.015% Mo which remains unchanged
from WLR Consulting’s (WLRC’s) April 21, 2006 Technical Report. The
estimate of inferred mineral resources above a 0.2% Cu cut-off also
remains unchanged at 145 million tons grading 0.45% Cu and 0.015% Mo.
Note: The PA is preliminary in nature
and includes the use of inferred resources that are considered too
speculative geologically to have economic considerations applied to them
that would enable them to be categorized as mineral reserves. Thus,
there is no certainty that the preliminary assessment will be
realized.
“The completion of a Preliminary
Assessment demonstrating the outstanding economic potential of the
property marks an important milestone in the development of the Rosemont
deposit.” reports Augusta President and Chief Executive Officer, Gil
Clausen. “We are extremely pleased with the results which confirm our
belief that Rosemont is one of the best undeveloped open pit copper
projects in the world and one of the largest undeveloped open pit copper
projects in the United States. Based on results of the PA and the
current and future projected demand for these strategic minerals,
Augusta will move forward to complete a final Feasibility Study.”
Preliminary Assessment Report Features:
The measured, indicated and inferred
resources reported in the Company’s National Instrument (“NI”) 43-101
Technical Report dated April 21, 2006, were used in the study. Results
of the Company’s current in-fill drilling and assay program are pending
and were not included in the PA. The Rosemont Deposit project was
evaluated under two scenarios (a) producing a copper concentrate product
only (Case 1); and (b) producing a cathode copper product from oxide
leaching and concentrate leaching, as well as some copper concentrate
sales (Case 2). The project was evaluated with an open pit mine design
optimization using a $1.05/ pound copper price to generate six initial
conceptual phases (pushbacks) that will be mined over a 16 year period
at a stripping ratio of 1.55 to 1 in the Case 2 and 1.9:1 when oxide is
considered unrecoverable in the Case 1.
Project Economics
Washington Group International Inc.
developed the economic model from which the following results were
obtained. Using base case metal prices of $1.20/lb. Cu, $10/lb. Mo and
$7.50/oz. Ag, the inclusion of capital contingencies of $83M (Case 1)
and $105M (Case 2), and a discount rate of 8%, the Case 1 project has a
Net Present Value (“NPV”) of $442M, and an Internal Rate of Return
(“IRR”) of 17%; Case 2 has NPV $494M, IRR 17%. Cash costs are estimated
at $0.42/lb. for Case 1, and $0.37/lb. for Case 2 with molybdenum and
silver by-product revenues netted against cash operating costs. Recent
metal prices for copper, molybdenum and silver are considerably higher
than the base case assumptions, the sensitivity chart below uses 3 year
trailing average and a combination of three year trailing average with 2
year forward copper prices. (See Technical Report for additional
sensitivity analyses on capital costs, operating costs and revenue.)
The TSX Venture Exchange does not
accept responsibility for the adequacy or accuracy of this release. For
additional information, contact the Company
Suite 400 - 837 West Hastings Street,
Vancouver, BC, V6C 3N6 Telephone: 604 687 1717, Facsimile: 604 687 1715,
E-mail: info@augustaresource.com
Case 1 (Concentrate production only)
| Case |
Cu |
Mo |
Ag |
IRR |
NPV |
NPV |
NPV |
Net |
| |
Price |
Price |
Price |
% |
5% |
8% |
10% |
Cash |
| |
$/lb |
$/oz |
|
US $ |
US$ |
US $ |
Cost |
| |
$/lb |
|
| |
|
$/lb |
| |
|
|
|
millions |
millions |
millions |
| |
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| Base |
1.20 |
10.00 |
7.50 |
17 |
715 |
442 |
306 |
0.42 |
| |
|
|
|
|
|
|
|
|
| Trailing |
1.50 |
20.00 |
7.50 |
28 |
1,481 |
1,044 |
827 |
0.20 |
| |
|
|
|
|
|
|
|
|
| Forward |
2.14 |
20.00 |
7.50 |
40 |
2,410 |
1,774 |
1,456 |
0.21 |
| |
|
|
|
|
|
|
|
|
• Trailing Case Prices, as of 5/31/06:
o Cu - average of 3 years trailing LME cash official prices
oMo - average of 3 years trailing price data for molybdenum oxide, F.O.B. North America.
oAg – constant $7.50/oz
•Forward Case Prices, as of 5/31/06:
oCu - average of the LME 27 month official forward price and 3 years of trailing LME official
cash prices.
o Mo – same as Trailing Case Prices o Ag – same as Trailing Case Prices
Case 2 (Cathode and Concentrate production)
| Case |
Cu |
Mo |
Ag |
IRR |
NPV |
NPV |
NPV |
Net |
| |
Price |
Price |
Price |
% |
5% |
8% |
10% |
Cash |
| |
$/lb |
$/oz |
|
US $ |
US$ |
US $ |
Cost |
| |
$/lb |
|
| |
|
$/lb |
| |
|
|
|
millions |
millions |
millions |
| |
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| Base |
1.20 |
10.00 |
7.50 |
17 |
807 |
494 |
337 |
0.37 |
| |
|
|
|
|
|
|
|
|
| Trailing |
1.50 |
20.00 |
7.50 |
26 |
1,589 |
1,112 |
873 |
0.16 |
| |
|
|
|
|
|
|
|
|
| Forward |
2.14 |
20.00 |
7.50 |
37 |
2,554 |
1,874 |
1,533 |
0.17 |
| |
|
|
|
|
|
|
|
|
•Trailing Case Prices: Same as Base Case
•Forward Case Prices: Same as Base Case
Environmental
Five fundamental characteristics set
the Rosemont Project operating plans apart from other copper mines in
the area: isolated location, project size, sustainable water supply,
water conservation, and dry tailings disposal. The proposed mining
facilities are located entirely within the Barrel Basin, with the pit
located on private lands within this isolated drainage. The land
requirements for the Rosemont project will total less than 4,000 acres,
which is less than a third of the 13,272 acres of public land sought by
earlier mining companies. Water conservation programs use the best
available modern technology to reduce water needs to
less than a third of other large copper
mines in the area. Dry tailings management technologies will conserve
water as well as eliminate the need for construction of a large
conventional tailings impoundment. These five characteristics of the
Rosemont project are expected to facilitate the permit review and
approval process.
In addition, Augusta proposes to
utilize concurrent reclamation with construction and re-vegetation of
perimeter berms along the outside of the waste rock storage areas,
within the first few years of mine operation. Augusta has used viewshed
analyses in the planning process to optimize locations and profiles of
facilities for minimal visual impact.
Incorporating best available
demonstrated control technologies, concurrent reclamation, and utilizing
a sustainable water supply; the Company is scheduled to initiate the
formal permit application and review process for the proposed low
profile mine during July 2006.
Mining & Production
The mining process at Rosemont will be a
conventional modern hard rock open pit operation. The open pit mine,
concentrator and leaching facility will include a nominal concentrator
production capacity estimated at 75,000 tons per day. The proposed
Rosemont mine is expected to annually produce 226 to 233 million pounds
of recovered copper, approximately 5.1 million pounds of recovered
molybdenum and approximately 6.7 million ounces of recovered silver as a
by-product credit over the mine life.
Infrastructure
The Rosemont project is located in Pima
County, approximately 50-km southeast of Tucson, Arizona accessible by
Highway 83. There are two available power lines located within 10 miles
and rail within 15 miles. The city of Tucson has an experienced
workforce for mining as four large open pit copper mines have operated
for decades within 25 miles of Rosemont. All infrastructure capital and
operating costs are included in the economic analysis.
Capital Costs
Direct capital costs (“CAPEX”) for the
project are estimated at $636M for Case 1 and $806M for Case 2. CAPEX
estimates include all infrastructure, mine and concentrator costs, as
well as a capital contingency totaling $83M (Case 1) and $105M (Case 2).
The additional costs in Case 2 include production of cathode copper
oxide heap leach from lined pads and also includes a copper concentrate
leach circuit allowing for approximately 75% of the copper contained in
the sulphide concentrate to report in solution to an SX/EW plant on site
that would be designed to handle a blend of solutions from the oxide
leach pads and the concentrate leach circuit. There was a 15%
contingency provision included in the capital estimate.
Operating Costs
The PA results indicate that the
Rosemont deposit may be a very low cost copper producer. The pretax cash
costs are estimated to be $0.42/lb of copper produced under Case 1, and
$0.37/lb for Case 2. Operating costs in Case 2 include acid costs,
leach pad operation and the costs associated with concentrate leaching
and running the SX/EW plant.
Next Steps
The PA marks the beginning of the
detailed development process for mining and production operations at
Rosemont. The Company is embarking on a final Feasibility Study
scheduled for completion early in 2007. In March 2006, the Company
commenced a 20,000-meter exploration, in-fill and geotechnical drilling
campaign on the Rosemont deposit with five drill rigs currently in
operation. A NI 43-101 Technical Report on PA results has been filed
under the Company’s profile on SEDAR at www.sedar.com, as well as at www.augustaresource.com.
The PA has been completed following one
year of current exploration by the Company at the Rosemont Property,
and should be read in conjunction with the NI 43-101 compliant Mineral
Resource Estimate and Technical Report for the Rosemont Deposit dated
April 21, 2006, which was completed by WLR Consulting, Inc. (see news
release dated January 24, 2006), and accessible on the Company’s website
at www.augustaresource.com or on SEDAR at www.sedar.com.
The PA is based on NI 43-101 Mineral Resource Estimate of 6.4 billion
lbs of Cu equivalent (442,000,000 tons at 0.73% Cu equivalent) in
measured and indicated resources and 1.9 billion lbs of Cu equivalent
(145,000,000 tons at 0.67% Cu equivalent) in inferred resources. Please
refer to the Company’s January 24, 2006, news release which provides
supporting information for equivalence. The PA
is preliminary in nature and includes the use of inferred resources
that are considered too speculative geologically to have economic
considerations applied to them that would enable them to be categorized
as mineral reserves. Thus, there is no certainty that the preliminary
assessment will be realized.
The PA was prepared by an integrated
engineering team that included Washington Group InternationalInc.,WLR
Consulting Inc., and Augusta personnel. Washington Group International
Inc., an integrated engineering, construction and management company
headquartered in Boise, Idaho, was retained as the primary author of the
preliminary assessment study. The PA was conducted under the overall
review of Mr. John Ajie, P.E., of Washington Group International Inc.,
an independent Qualified Person under the standardssetforthbyNI43-101.
ABOUT AUGUSTA RESOURCE CORPORATION -
Augusta Resource Corp. is a mineral exploration and development company
responsibly advancing copper and other base metal assets in the U.S.
southwest. The Company’s Rosemont Property is located in Pima County,
approximately 50 km southeast of Tucson, Arizona, and contains four
known potentially open-pit copper/molybdenum deposits. The Rosemont
deposit contain 6.4 billion lbs of Cu equivalent (442,000,000 tons at
0.73% Cu equivalent) in measured and indicated resources and 1.9 billion
lbs of Cu equivalent (145,000,000 tons at 0.67% Cu equivalent) in
inferred resources. Please refer to the Company’s news release dated
January 24, 2006 for further details. Augusta has additional exploration
properties in Nevada. The Company is traded on the Canadian TSX Venture
Exchange under the symbol ARS.
For additional information please visit www.augustaresource.com or contact:
ON BEHALF OF THE BOARD OF DIRECTORS
“Gil Clausen”
_________________________
Gil Clausen
President and CEO
SPECIAL NOTICE REGARDING FORWARD-LOOKING STATEMENTS
Certain of the statements made and
information contained herein and in the documents incorporated by
reference may contain “forward-looking statements” including statements
concerning the Company’splansatitsRosemont Property, and other mineral
properties, which involve known and unknown risks, uncertainties and
other factors which may cause the actual results, performance or
achievements of the Company, or industry results, to be materially
different from any future results, performance or achievements expressed
or implied by such forward- looking statements. Forward-looking
statements are subject to a variety of risks and uncertainties which
could cause actual events or results to differ from those reflected in
the forward-looking statements, including, without limitation, risks and
uncertainties relating to the interpretation of drill results and the
estimation of mineral resources and reserves, the geology, grade and
continuity of mineral deposits, the possibility that future exploration,
development or mining results will not be consistent with the Company’s
expectations, metal recoveries, accidents, equipment breakdowns, title
matters, labor disputes or other unanticipated difficultieswith or
interruptions in production, the potential for delays in exploration or
development activities or the completion of feasibility studies, the
inherent uncertainty of production and cost estimates and the potential
for unexpected costs and expenses, commodity price fluctuations,
currency fluctuations, failure to obtain adequatefinancingona timely
basis and other risks and uncertainties, including those described under
Risk Factors Relating to the Company’s Business in the Annual
Information Form and the management’s discussion and analysis.Shouldone
or more of these risks and uncertainties materialize, or should
underlying assumptions prove incorrect, actual results may vary
materially from those described in forward-looking statements.
Accordingly,readersareadvised not to place undue reliance on
forward-looking statements. Forward- looking statements include
statements regarding the expectations and beliefs of management, the
assumed long-term price of copperandexchangerates, the estimation of
mineral reserves and resources, the realization of mineral reserve
estimates in future expected production, anticipated future capital and
operating costs, and the potential of the Company’s properties and
expectations of growth. Except as required under applicable securities
legislation, the Company undertakes no obligation to publicly update or
revise forward-looking statements, whether as a result of new
information,future events or otherwise.